Completion of 03 project under Namami Gange Programme, the details of which is as follows : -

S. No. Name of Projects Sanctioned Cost (cr.) STP capacity (MLD)
1 I &D works & STP works for Naini, Phaphamau and Jhunsi in Prayagraj (HAM) 767.60 72
2 I&D and STP works at Jaunpur  (DBOT) 206.05 30
3 I&D and STP works at Budahana , Distt Muzzafarnag (HAM) 48.76 10
  Total   142

The progress of ongoing 14 Namami Gange projects in this duration is as follows: -

S. No. Name of Projects No. of STPs STP capacity (MLD) Physical Progress till 01.04.2023 Physical Progress till 01.03.2024
1 I&D and STP works at Budhana town, Distt. Muzaffarnagar (HAM) 1 10 87.07 % 100.0 %
2 I&D and STP works at Muzaffarnagar (HAM) 2 54.50 78.35 % 92.19 %
3 I&D and STP works at Unnao  (HAM) 1 15 94.40 % 95.50 %
4 I&D and STP works at Shuklaganj, distt. Unnao (HAM) 1 5 65.0 % 80.25 %
5 I&D and STP works at Sultanpur (DBOT) 3 17 95.95 % 99.80 %
6 I&D and STP works at  Kairana  (DBOT) 1 15 60.65 % 88.44 %
7 I&D and STP works at Lucknow (DBOT) 2 42.50 28.10 % 74.32 %
8 I&D and STP works at Mirzapur (HAM) 2 17 50.0 % 98.0 %
9 Sewerage works at Ghazipur (HAM) 1 21 42.0 % 97.0 %
10 I&D and STP works at Fatehgarh - Farrukhabad (HAM) 3 45 33.50 % 82.50 %
11 I&D and STP works at Bareilly (HAM) 3 63 53.98 % 95.0 %
12 I&D and STP works at Moradabad (HAM) 1 25 1.0 % 43.0 %
13 Rehabilitation/Renovation of Agra Sewerage Scheme (I&D works) (HAM ) 13 177.60 2.0 % 35.98 %
14 I&D and STP works at Ayodhya (HAM) 1 33 7.50 % 77.89 %
  Total 35 540.60    

1. Commissioning of 7 STPs having capacity 107.50 MLD ( Sultanpur- 2 MLD, Bareilly – 21 (20 +1) MLD, Muzzafarnagar- 54.50 (22+32.50) MLD, Unnao-15 MLD and Kairana- 15 MLD) has also been completed. In addition to above, 4 new projects (4 STPs – 378 MLD) tender is finalized and issued LOA for Meerut, Mathura ,Varanasi and Prayagraj.

2. Total expenditure, amounting Rs. 755.30 cr. (HAM/DBOT) was incurred in the ongoing Namami Gange Projects.

Sanction of 06 new projects under Namami Gange Programme, the details of which are as follows: -

S. No. Name of Projects Date of Sanction Sanctioned Cost (cr.) STP capacity (MLD)
1 I & D and STP works at Shamli (DBOT) 25.05.2023 206.02 40
2 I & D and STP works at Thanabhawan  Town Distt- Shamli (DBOT) 25.05.2023 97.19 10
3 I & D and STP works at Banat Town Distt- Shamli (DBOT) 25.05.2023 48.71 05
4 I & D and STP works at Babri-Banti Khera village Town Distt- Shamli (DBOT) 25.05.2023 55.47 05
5 I & D of 02 drains and augmentation of Naini STP at Prayagraj (DBOT)   05.09.2023 186.47 50
6 I&D and STP works at Lucknow, Phase-II, Part-II (HAM)   19.09.2023 351.03 100
7 I&D and STP works at Hapur (DBOT) 05.09.2023 49.06 06
  Total   993.95 216